What is it: 8D Report is a
structured step-by-step problem solving methodology for product and process
improvement. The 8D Report involves identifying the root cause of a problem
using data collection and data analysis, taking actions to resolve the problem,
and preventing similar problems from occurring in the future. The 8D
Report is structured into eight specific steps which require team synergy.
Hence, the philosophy behind 8D is that the team as a whole is better and
smarter than the quality sum of an individual.
Why use it: The primary difference
between the 8D Report and other problem-solving approaches is the emphasis on
involving the collective skills and knowledge of the TEAM versus doing it all
yourself.
When to use it: The 8D Report is a
problem solving tool for product and process problematic non-conformance's and
improvement activities, ideally used for complex or urgent issues which an
individual is unable to solve with a quick fix.
How to use it: The 8D Report
consists of the 8 following steps below, please refer to the instruction
presentation in the 8D Report template package for a more detailed explanation:
1D
ESTABLISHING THE TEAM
First step is establish the team
consists of few persons, that will be responsibility for realised particular
step of 8D. Quantity of team and their making-up depends of complexion of the
problem and taken decision.
The team should fulfil the
following steps:
1. Have a good knowledge of the
product and processes.
2. Multidisciplinary – that’s mean
person with different department: Engineers (designers ), Technologists
(production), Rework operator, , production staffs, Quality Engineers, Buyers, Others
3. Have adequate capability to
introduce proper solution of the problem.
4. The team should have a Leader,
who supervises and closes 8D.
2D
Problem description
This is the stage where you need to
most accurately describe the problem. Properly problem description is the
starting point to further step of analysis and proper understanding of the
nature of the problem for the Team as well as people from outside.
It’s recommend that description of
the problem include:
1. Properly described the problem.
Not restricted to laconic statements.
2. Place problem detected.
3. Scale of problem, eg. % of
reject or qty of pcs / range deviations beyond the tolerance etc.
4. It’s very important that problem
was „measurable” that is how many % or ppm or in another unit of measure.
5. Later this allows to properly
assess whether corrective actions are implemented efficiently or not.
3D
Containment action
This is the stage where are taken
right containment action to prevent escalation of the problem (further making
defects) or at the worst delivering not conforming products to the customer.
Example of action:
1. Stoppage of production /
shipment
2. Additional visual control
3. Informing the Customer about the
problem (for verification of the goods at the Custom.)
4. Segregation goods on OK / NOK
5. Informing operators about the
problem
6. Check if similar products or
processes, there is a similar risk (if yes – should be implemented the
containment action)
4D
Root Cause
To really eliminate the problem
should be identify the real cause of the problem “root cause”. This is not a
simple issue. This is why it is important the Team’s work to look at the
problem with few sites. Often the real causes of many problems are deep in the management
of the company.
The production process often throws
up the cause of the problem on “operator error”. It is a mistake. The reasons
are much deeper:
1. Lake
of properly tools.
2. Lake
of training or training aren’t efficient.
3. Overtime work in hurry (effect
of wrong decisions of the management).
4. The production process is not
suitable for quality requirements.
5. The others.
4D
Root Cause
Define the cause of the problem
using 5-WHY methodology (WHY 5 times)
Cause: A lot of short circuit on
connector’s legs on PCB (after wave soldering
1-WHY: Why problem occurred? To
less flux putting on pbca surface (that was the root cause of short circuits).
2-WHY: Why problem occurred? Wave
soldering machine adjustment (flux amount) incorrect set up
3-WHY: Why problem occurred? Operator
/ Technologist didn’t know how process improvement.
4-WHY: Why problem occurred? Operator
/ Technologist training is incorrect (no efficiently). .
5-WHY: Why problem occurred? No standard training material and no trainer
to assure high level of Operators / Technologists knowledge.
If we identify the cause of the
problem correctly then “eliminate” the root cause allows to really solve the
problem and often many others
5D
Corrective action
The Team determines which actions
should be introduced in the short period of time to ensure that the process /
product is controlled.
Examples:
1. Introducing additional control
in process
2. Introducing additional other
process (eg. Component reworked, test corrected)
3. Rework defective units found
inside
4. Rework units returned from
Customer
5. Inform the Supplier about
defective part delivered and their Exchange, etc.
6D
Validate corrective action
Please verify that the corrective
actions taken are efficiently. It should be based on “ real data” from the
process. Action should not be estimated on the basis of only the same opinion
of the persons interested
Examples:
1. Less reject % (ppm) in process.
2. Test / control results shows
improvement.
3. Engineering’s measurements (dimension,
units appearance ) are correct (according to tolerance, specification).
4. Other proofs shows on
Introducing corrective action.
5. Supplier delivers goods of
better quality.
7D
Prevent recurrence
Next step is is to determine what
action should be taken to prevent recurrence of the problem. Here we define the
action system to replace the actions defined in 5D.
Examples:
1. Modified or make proper jig
(tooling).
2. Changing the process parameters
in order to prevent defects.
3. Changing process / tools by
Supplier which make parts.
4. Changing procedures
(organisation change).
5. Changing documentation /
specification (if was incorrect).
6. Preparing systematic and full
training for staff.
8D
Verify and congratulate Team
The last step is verified that the
introduced actions in 7D are effective. It is
recommended that verification be
made by comparing the scale of the problem (as described in 2D) with results
from next deliveries of material or results from rejecting of next batches.
The verification must be based on
that measurable data. Leader of the
Team is made verification During the verification it is worth to draw
conclusions as the Team worked, what the individual members have learned and
what are the conclusions for future – what can be improved on problem solving,
etc.